Transmission Annual Planning Report
ElectraNet’s Transmission Annual Planning Report (TAPR) provides information to market participants and other interested parties on the current capacity and emerging limitations of the South Australian transmission network over a 10-year planning period.
The report helps potential loads and generators to identify and assess opportunities in the market. It also includes demand forecasts and information on completed, committed and proposed transmission network developments.
We welcome feedback on the report’s findings. Proponents of non-network solutions are invited to propose alternative options to meet future network needs.
ElectraNet has published its 2023 Transmission Annual Planning Report (TAPR). The report highlights that the electricity demand outlook in South Australia is growing driven by electrification of the economy and new industrial loads. South Australia has an abundance of renewable energy resources to meet increased demand that can be unlocked with additional capacity in the transmission network.
ElectraNet has identified the Integrated System Plan project, Mid North SA Renewable Energy Zone, as critical to South Australia fully capitalising on the global green transition.
ElectraNet is seeking feedback on the findings of the TAPR which can be submitted to consultation@electranet.com.au by 13 December 2023. We are also hosting an online forum on 6 December 2023 and registrations can be made here.
2023 ElectraNet Transmission Annual Planning Report
Historic_load_trace_MVA_TGCP023
Historic_load_trace_MVA_TGTL017_2023
Historic_load_trace_MW_TGCP023_2023
Historic_load_trace_MW_TGTL017_2023
New generator connection data as of 31 Oct 2023
- 2021 ElectraNet Transmission Annual Planning Report
- 2021 Connection point data
- 2021 Connection point historical load data MVA
- 2021 Connection point historical load data MW
- 2021 Transmission line data
- 2021 Transmission line segment flow historical data MVA
- 2021 Transmission line segment flow historical data MW
- New generator connection data as of 2 November 2021
- 2020 ElectraNet Transmission Annual Planning Report
- 2020 Highlights
- 2020 Transmission Annual Planning Report Interactive Map
- 2020 Connection point data
- 2020 Connection point historical load data MVA
- 2020 Connection point historical load data MW
- 2020 Transmission line data
- 2020 Transmission line segment flow historical data MW
- 2020 Transmission line segment flow historical data MVA
- New generator connection data as of 26 October 2020
- 2019 Transmission Annual Planning Report (TAPR)
- 2019 Transmission Annual Planning Report Interactive Map
- 2019 Connection Point Data
- 2019 Transmission Line Data
- 2019 Connection Point Load MW
- 2019 Connection Point Load MVA
- 2019 Transmission line segment flow data
- 2019 New Generator Connection Data – as of 23 June 2020
- 2019 New Generator Connection Data – as of 31 May 2019