Project Overview
The upgrade of Kadina East substation will meet the increasing electricity demands of the area by replacing the sole transformer onsite with two increased capacity 132/33kV transformers, associated switchgear, secondary systems and telecommunications.
It is proposed to overcome a projected connection point limitation at the Kadina East substation by expanding the existing substation and installing two 60MV.A 132/33kV transformers, establishing a 132kV bus and installing secondary systems and telecommunications with the provision for remote control data collection and national grid metering.
Construction works for the new 132/33kV Kadina East substation at the corner of Mundinna and Helston Roads commenced in July 2010 and will continue through until June 2011 when the upgrade works become operational.
RIT-T
Reports | Closing Dates | Status | Submissions |
---|---|---|---|
Application Notice | Consultation Closed |
|
|
Final Report | Consultation Closed |
|