Project Overview

This development replaced ageing 132kV transmission lines north of the existing Bungama substation and replaced the existing 132kV substation section at Bungama which prevents overloading of the Brinkworth 275/132kV transformer.

This transmission solution established a new 275/132kV substation section, removed the superseded 132/33kV substation, and established a new 275kV line connection with removal of the aged 132kV lines between Bungama and Playford substations.

RIT-T

Reports Closing Dates Status Submissions
Request for Information Consultation Closed
  • -
Application Notice Consultation Closed
  • -
Final Report Consultation Closed
  • -