A process has been established for the resolution of RIT-T disputes, including the required timeframe for the lodgement of a dispute submission.

Should any relevant parties seek to challenge the conclusions of a Project Assessment Conclusions Report, ElectraNet will seek to resolve the issue in accordance with Clause 5.6.6A of the National Electricity Rules and the Regulatory Investment Test for Transmission Application Guidelines published by the AER in June 2010.

A dispute must be lodged with the AER and ElectraNet within thirty days of ElectraNet publishing the Project Assessment Conclusions Report.