Project Overview

Project rescheduled to 2024, due to lower demand forecast. The Regulatory Investment Test for Transmission (RIT-T) process commenced in the second half of 2012. However, this project will not be continued at present due to lower demand forecast.

Options will be assessed using the RIT-T process.

Planned Energisation: November 2024

 

RIT-T

Reports Closing Dates Status Submissions
Project Specification Consultation Report Consultation Closed
  • -

Managing Voltages on the Mid North transmission system

This Project Specification Consultation Report (PSCR) addresses forecast voltage limitations and inadequate reactive power margins in the Mid North re...