Project Overview

After almost 50 years in service, the Eyre Peninsula’s existing high-voltage power line is approaching the end of its operational life. To ensure the Eyre Peninsula has a secure and reliable electricity supply for the next 50 years, ElectraNet is building a new high-voltage power line and upgrading five substations.

 

About the project

Eyre Peninsula Link involves the construction of a new, double-circuit 132 kV transmission line from Cultana to Port Lincoln, via Yadnarie, with the ability to upgrade the Cultana to Yadnarie section to 275 kV at a later date.

EPBC Approval

The Eyre Peninsula Link transmission line has been approved under the EPBC Act. The controlling provisions are listed threatened species and communities (section 18 and 18A of the EPBC Act). Management Plans have been prepared to manage impacts on threatened species and communities and are available for download below:

Malleefowl Management Plan

Weed Pest and Disease Management Sub Plan

Threatened Species Management Plan

Response to public comment

The Eyre Peninsula Link transmission line is controlled under the EPBC Act and is being assessed by preliminary documentation. The controlling provisions are listed threatened species and communities (section 18 and 18A of the EPBC Act). Proposed construction activities have the potential to impact on Malleefowl (Leipoa ocellata), Jumping Jack Wattle (Acacia enterocarpa) and Tufted Bush Pea (Pultenaea trichophylla).

In accordance with Section 95A(3) of the EPBC Act, ElectraNet made the preliminary documentation  available for public comment from 17 December 2020 to 11 January 2021. No public submissions were received on the Preliminary Documentation during this time.

In accordance with Section 95B(4) of the EPBC Act, written advice noting that no comments were received, the original EPBC referral document and the Preliminary Documentation is available for information for 20 business days from the date of advertisement.

Copies of the Preliminary Documentation can be viewed or downloaded below:

EPBC Referral

EPBC Preliminary Documentation

Noting the current COVID 19 safety measures, anyone requiring hard copies of the preliminary documentation is encouraged to contact ElectraNet and a copy will be sent to you without charge. For hard copies contact:

Alecia Wright
Senior Development Adviser
wright.alecia@electranet.com.au
PO Box 7096 Hutt Street Post Office, ADELAIDE SA 5000

People with specific needs (i.e. for whom have low literacy in English or people living with a disability) may contact 0439 758 888 for assistance with the material.

Benefits of the new line

The new line will provide homes and businesses throughout the Eyre Peninsula with a secure and reliable power supply. Other benefits of the project include:

  • increasing capacity to connect more users to the electricity network;
  • enabling new renewable energy projects to connect in the future;
  • opportunity to extend the network in future; and
  • during construction, workers spending money in the communities they’re working in.

Project work opportunities

In August, ElectraNet and Downer Infrastructure Projects, hosted two successful Local Industry Briefings for businesses interested in getting involved in the project.

 These briefings were an opportunity for businesses to learn about the project, tendering process, work packages and how to get involved.

As at late June 2021 we are pleased to report that nearly 60% of all subcontracts awarded for the EPLink project have been awarded to South Australian businesses with 25% of these awarded to Eyre Peninsula based businesses:

There may still be limited opportunities for local Business involvement.
Businesses wanting to register their interest can click here.


Line route

The route of the new line runs almost parallel to the existing transmission line, on its western side. The route was identified through engineering, research, technical field studies and direct engagement with landowners and the broader Eyre Peninsula community.

As part of the project, some temporary transmission lines will be constructed which will ensure power supply can be maintained to the Eyre Peninsula while the new line is being built.

Route characteristics

The chosen route achieves the best balance of environmental, cultural, social, land use, engineering and cost criteria. The transmission line route:

  • Reflects community preferences to contain the new and old infrastructure within the same corridor, to the west of the existing line. This was the strongest preference in landowner feedback to ElectraNet.
  • Has the least environmental impact by using existing access tracks to minimise vegetation clearance.
  • Minimises impacts on culturally sensitive sites. Cultural heritage will be managed through a specific Aboriginal Cultural Heritage Management Plan.
  • Achieves the lowest cost for consumers as it is the shortest, most direct route between its fixed connection points.

Current status

Project construction commenced in March 2021. ElectraNet and it contractor Downer Group will continue to engage with landholders to discuss access to their property during construction and answer questions they may have.

Project timing

Construction on the new transmission line is expected to be completed and the line energised by late 2022. 

Working with landholders and the community

ElectraNet will continue to engage directly with landowners along the project corridor to manage possible issues such as access, timing, vegetation removal and rehabilitation. We will also be in the field collecting environmental and engineering information to ensure the project’s successful delivery.

Removal of old power line

At this stage, most sections of the existing line will remain and be maintained.

More information

For any queries, feedback or to be kept updated on the project, please contact ElectraNet’s Community
Engagement Consultant at community.liaison@electranet.com.au or call toll-free on 1800 890 376.

Project Information Sheet - June 2020 (PDF, 1 MB)
Project Information Sheet - July 2021 (PDF, 1 MB)
 
 

Release of Project Specification Consultation Report (PSCR)

 

Release of Project Assessment Draft Report (PADR)

 

Release of Project Assessment Conclusions Report (PACR)

 

Australian Energy Regulator RIT-T approval

 

Submission of Contingent Project Application (CPA)

 

CPA approval from Australian Energy Regulator

 

Construction work begins

 

New line energised